Why Earned Value Management Matters

August 30, 2024 | 12 min read

In this article

  • What is Earned Value Management?

  • EVM Benefits

  • What Projects Can Benefit from EVM?

  • How to Calculate Earned Value in Project Management

  • EVM Implementation Steps

  • Earned Value Management Restrictions

  • EVM Best Practices

  • Using EVM Software in Project Management

  • Earned Value Management Certifications

Every manager wants a clear understanding of the status of their project and answers to questions such as: is the project behind or ahead of schedule, how efficiently are resources used, is the budget exceeded or is there any savings, what is the cost of the remaining work? Its components and processes must be carefully managed for a project to succeed. The project manager needs constant feedback to spot potential problems in time and solve them to complete everything on time and within budget. Earned Value Management (EVM) technique helps to cope with these tasks. It integrates the analysis of the entire scope of work on the project with the work execution plan and the cost of its implementation. Thanks to it, you can monitor the primary metrics of the project status and assess the actual state of affairs, making the necessary management adjustments.

What is Earned Value Management?

EVM is a powerful project management technique that provides a comprehensive overview of project performance. By integrating scope, schedule, and cost metrics, EVM enables project managers to assess project progress, identify potential issues early, and make informed decisions. It is also known as earned value project management or earned value performance management (EVPM).

EVM Benefits

Earned Value Management offers numerous benefits for project managers and organizations:

  • Improved decision-making: EVM provides data-driven insights that support informed decision-making throughout the project lifecycle.

  • Enhanced project control: Earned Value Management enables proactive management and adjustments by tracking project performance against planned metrics.

  • Early identification of issues: EVM can detect potential problems, allowing for timely corrective actions.

  • Improved communication: Earned Value Management facilitates effective communication with stakeholders by providing a common language and framework for discussing project progress.

  • Increased accountability: EVM can help increase accountability among team members by providing a transparent view of project performance.

  • Enhanced stakeholder satisfaction: Earned Value Management improves stakeholder satisfaction by regularly updating project progress and proactively addressing issues.

  • Improved resource allocation: EVM can help optimize resource allocation by identifying areas where resources may be over- or underutilized.

  • Enhanced risk management: Earned Value Management helps identify and mitigate risks impacting project performance.

What Projects Can Benefit from EVM?

Earned Value Management can be applied to a wide range of projects, but it is particularly beneficial for:

  • Large-scale projects: Projects with complex scopes, multiple stakeholders, and budgets can significantly benefit from EVM's ability to track progress and identify potential issues early.

  • Projects with tight deadlines: Earned Value Management can help project managers monitor progress closely and adjust as needed to ensure timely delivery.

  • Projects with uncertain scope or requirements: EVM can help project managers adapt to changes and maintain control over project performance.

  • Projects with multiple stakeholders: Earned Value Management can facilitate transparent communication and stakeholder accountability.

  • Projects focused on cost control: EVM provides valuable insights into project spending and helps identify areas for cost savings.

How to Calculate Earned Value in Project Management

Earned Value (EV) is a powerful metric to assess project performance. It measures the value of work completed against the planned budget. To calculate EV, you multiply the percentage of completed work by the original budget allocated to that work.

How to calculate EV:

  1. Determine the Planned Value (PV): This is the budgeted cost of work scheduled to be completed by a specific point in time.

  2. Calculate the % of work completed: Estimate the percentage of the project's scope that has been finished.

  3. Calculate EV: Multiply the % of work completed by the PV.

Formula:

  • EV = % of work completed * PV

Example:

If a project has a total budget of $300,000 and is 70% complete, the earned value is:

  • EV = 0.7 * $300,000 = $210,000

EVM Metrics

Earned Value Management offers a standardized approach to measuring project performance. By comparing EVM metrics, project managers can objectively assess whether a project is ahead, on, or behind schedule and budget. This information is essential for holding team members accountable and making the right decisions about resource allocation and project adjustments.

Primary Metrics

At the heart of Earned Value Management lies a trio of fundamental metrics: Planned Value (PV), Actual Cost (AC), and Earned Value (EV). These form the basis for assessing project performance and progress.

  • Planned Value (PV): The authorized budget for the work expected to be completed at a particular time.

  • Earned Value (EV): The value of the work completed to date, measured in terms of the budget.

  • Actual Cost (AC): The total costs incurred to complete the work at a specific point in time. Track the AC to have a more precise picture of the project status.

Additional Metrics

Beyond the three primary metrics, Earned Value Management incorporates several additional metrics to provide a more comprehensive view of project performance. These metrics offer valuable schedule, cost, and overall project health insights.

  • Cost Variance (CV): Indicates whether the project is over or under budget.

  • Schedule Variance (SV): Indicates whether the project is ahead of, on, or behind schedule.

  • Cost Performance Index (CPI): Measures the efficiency of project spending.

  • Schedule Performance Index (SPI): Measures the efficiency of project scheduling.

  • To-Complete Performance Index (TCPI): Predicts the future performance required to complete the project within the original budget and schedule.

  • Estimate At Completion (EAC): Provides a revised estimate of the project's total cost based on current performance.

  • Estimate To Completion (ETC): Estimates the remaining cost to complete the project.

  • Variance At Completion (VAC): Provides an overall project performance assessment.

These metrics are then used to conduct further Earned Value Analysis (EVA) and evaluate your project from various perspectives. EVA is crucial in construction for effective project monitoring, cost control, objective performance measurement, and timely decision-making.

EVM Formulas

Have you ever spent hours figuring out if the value of the project you’re working on equals the amount of money you’re paying to complete it? With Earned Value Management and the following formulas, you’ll not have to wonder again.

 

Cost Variance (CV)

Cost Variance indicates whether the project is over or under budget. The difference between how much you planned to spend thus far and your actual costs. To calculate the CV, subtract the Actual Cost from the Earned Value. A positive CV is good news, while a negative CV indicates overspending.

Formula:

  • CV = EV – AC

Example:

If a project has a total budget of $70,000 and the actual cost is $90,000, the cost variance is:

  • CV = $70,000 - $90,000 = -$20,000  

In this example, the CV is negative, which means the project cost is too high.

 

Schedule Variance (SV)

Schedule Variance indicates whether the project is ahead of, on, or behind schedule. To calculate the SV, subtract the Planned Value from the Earned Value. A positive SV means you're ahead of schedule, while a negative SV indicates you're behind.

Formula:

  • SV = EV – PV

Example:

If the earned value is $53,000 and the planned value is $70,000, the schedule variance is:

  • SV = $53,000 - $70,000 = -$17,000

To get a percentage, divide the SV (-$17,000) by the PV ($70,000) = -0.2, -20%. This means the project is 20% behind schedule.

 

Cost Performance Index (CPI)

Cost Performance Index is a vital metric in EVM that assesses the project’s cost efficiency. CPI is calculated by dividing Earned Value by Actual Cost. A CPI greater than 1 is desirable, indicating you're getting more value for your money.

Formula:

  • CPI = EV / AC

Example:

If the earned value is $60,000 and the planned value is $95,000, the cost performance index is:

  • SV = $60,000 / $95,000 = 0,63

This means that your project is over budget.

 

Schedule Performance Index (SPI)

Schedule Performance Index is another crucial EVM metric that evaluates the project’s schedule performance. Monitoring the SPI helps project managers identify schedule deviations and make necessary adjustments. SPI is calculated by dividing EV by PV. An SPI greater than 1 means you're ahead of schedule.

Formula:

  • SPI = EV / PV

Example:

A project team completes 30,000 units out of a planned 60,000. Their SPI is calculated as follows:

  • SPI = 30,000 / 60,000 = 0,5

This shows that the team's progress is 50% complete.

 

To-Complete Performance Index (TCPI)

TCPI is a vital metric for all project stakeholders, particularly those facing budget challenges or potential risks. It answers the question, "How efficiently must we use our remaining resources to complete the project within budget?"

TCPI is a predictive metric that indicates the required efficiency level for a project to finish within its specified budget. It considers the project's current performance and remaining work to determine the necessary performance level for successful completion. This goal can be the original budget (BAC), a revised estimate (EAC), or a custom target set by management.

The following formula calculates TCPI for BAC:

  • TCPI = (BAC – EV) / (BAC – AC)

Use TCPI with BAC when:

  • You want to assess the overall project performance: TCPI with BAC provides a comprehensive view of the project's overall efficiency and the required future performance to achieve the original budget.

  • You have a stable project environment: If the scope and conditions remain relatively unchanged, TCPI with BAC can provide a reliable forecast.

The following formula calculates TCPI for EAC:

  • TCPI = (BAC – EV) / (EAC – AC)

Use TCPI with EAC when:

  • The project's scope or budget has changed: If the project has significantly changed, using EAC as the baseline can provide a more accurate assessment of future performance.

  • You want to evaluate the impact of recent changes: TCPI with EAC can help assess the effectiveness of recent corrective actions or changes to the project plan.

Example 1 (using BAC):

Where,

  • BAC = $100,000

  • EV = $70,000

  • AC = $80,000

Result:

  • TCPI = ($100,000 - $70,000) / ($100,000 - $80,000) = 1.5

To finish within the original budget, the project must be completed 50% more efficiently than its current performance.

Example 2 (using EAC):

Where,

  • BAC = $100,000

  • EV = $70,000

  • AC = $80,000

  • EAC = $120,000

Result:

  • TCPI = ($100,000 - $70,000) / ($120,000 - $80,000) = 0.75

To finish within the revised budget (EAC), the project must be completed 25% more efficiently than its current performance.

In this example, the TCPI with BAC is higher than the TCPI with EAC, indicating that the project will likely require more effort to finish within the original budget.

  

Estimate At Completion (EAC)

The EAC provides a revised estimate of the project's total cost based on current performance. It considers the project's planned value (BAC) and current cost performance (CPI) to predict the final cost.

Formula:

  • EAC = BAC / CPI

Example:

A project has a planned budget of $500,000, the current earned value is $350,000, and the actual cost is $400,000.

  • CPI = $350,000 / $400,000 = 0.875

  • EAC = $500,000 / 0.875 = $571,429

Considering the current performance, the estimated total cost to complete the project has escalated from the original budget of $500,000 to $571,429, indicating a potential budget overrun.

In this case, the EAC is higher than the BAC, suggesting the project is over budget.

 

Estimate To Completion or Estimate To Complete (ETC)

ETC estimates the remaining cost to complete the project and calculates the difference between the estimated total cost (EAC) and the actual cost incurred to date.

Basic formula:

  • ETC = EAC - AC

Alternative formulas:

  • ETC = Remaining Work

  • ETC = BAC - EV

  • ETC = (BAC - EV) / CPI

  • ETC = (BAC - EV) / (CPI * SPI)

Choose the appropriate formula based on your project's specific circumstances and the level of detail required.

Example:

Let's consider a project with a BAC of $1,000,000, an EV of $700,000, and an AC of $750,000.

First, calculate EAC:

  • EAC = BAC / CPI

  • CPI = EV / AC = $700,000 / $750,000 = 0.9333

  • EAC = $1,000,000 / 0.9333 = $1,071,429

Then, use it to calculate ETC:

  • ETC = EAC - AC

  • ETC = $1,071,429 - $750,000 = $321,429

Based on its current performance, the project is estimated to require an additional $321,429 to complete, which indicates that it is likely to overrun the original budget.

 

Variance At Completion (VAC)

VAC provides an overall assessment of project performance. It represents the difference between the estimated total cost (EAC) and the original budgeted cost (BAC).

Formula:

  • VAC = BAC – EAC

Example:

Let's calculate VAC for a project with a BAC of $1,000,000 and EAC of $1,200,000.

To calculate VAC:

  • VAC = BAC - EAC

  • VAC = $1,000,000 - $1,200,000 = -$200,000

The negative VAC of -$200,000 indicates that the project will overrun the original budget by $200,000, which means the project's final cost will exceed the planned budget.

EVM Implementation Steps

1. Define Project Scope and Objectives

Start by defining clear goals, deliverables, and a baseline for performance. Establishing a baseline for project performance provides a benchmark against which to measure progress and identify variances.

2. Create a Work Breakdown Structure (WBS)

A WBS breaks down the project into smaller, manageable tasks, making tracking progress and allocating resources easier.

Project managers can create a detailed project plan as the foundation for EVM calculations by assigning estimated durations and costs to each task. A well-structured WBS ensures that all project components are accounted for and provides a clear roadmap for execution.

3. Develop a Project Schedule

Create a timeline that outlines each task's start and end dates, considering dependencies between tasks and identifying potential risks that could impact the schedule. A well-planned schedule provides a roadmap for project execution and helps ensure timely completion.

4. Establish a Budget

By allocating a budget to each task based on its estimated cost, project managers can create a baseline budget for the entire project. This budget serves as a financial benchmark against which project performance can be measured. A well-defined budget helps ensure that resources are allocated effectively and the project is completed within the allocated funds.

5. Define Performance Measurement Baseline (PMB)

It serves as a benchmark against which project performance can be measured and managed. The PMB is established during the project planning phase and encompasses the project's scope, schedule, and cost parameters.

6. Track Progress Regularly

This step involves collecting data on actual work completed and costs incurred and then calculating key EVM metrics such as Earned Value, Planned Value, and Actual Cost.

7. Analyze EVM Metrics

Use EVM metrics to assess project performance, identify variances, and take corrective actions. Calculate CPI, SPI, CV, and SV to evaluate schedule and cost performance.

8. Communicate Regularly

Share EVM data and insights with stakeholders to keep them informed. Address any issues or concerns promptly.

9. Make Adjustments as Needed

If project performance deviates from the plan, make necessary adjustments to the schedule, budget, or scope.

10. Strive for Continuous Improvement

Review EVM data and processes regularly to identify areas for improvement. Learn from past projects and apply lessons to future initiatives.

Earned Value Management Restrictions

While EVM is a powerful tool for project management, it has certain limitations:

  • Data accuracy: EVM relies on accurate and up-to-date data. Inaccurate or incomplete data can lead to misleading results.

  • Complexity: EVM can be complex to implement and understand, especially for large projects with multiple work packages.

  • Cultural resistance: This resistance using EVM often stems from a combination of factors, such as a lack of understanding, fear of change, and perceived workload.

  • Subjectivity: Determining the percentage of work completed can sometimes be subjective, leading to variations in EV calculations.

  • Limited scope: EVM primarily focuses on schedule and cost performance and may not fully capture other important project factors, such as quality or risk.

EVM Best Practices

Effective implementation of Earned Value Management requires careful planning and adherence to best practices. Here are some key guidelines:

1. Data Accuracy and Consistency

Ensuring that Planned Value, Earned Value, and Actual Cost data are accurate and up-to-date is essential for reliable performance analysis. Additionally, using consistent definitions for work units and performance measurements helps maintain data integrity and facilitates accurate comparisons.

2. Regular Updates

By frequently collecting and analyzing data on Planned Value, Earned Value, and Actual Cost, project managers can stay informed about project progress, identify potential issues early, and make timely adjustments to the project plan as needed. This proactive approach helps ensure the project remains on track and achieves its objectives.

3. Integration with Project Management Tools

These tools streamline data collection, automate calculations, and provide valuable visualizations for tracking project performance. Such software allows project managers to save time, reduce errors, and better understand project progress.

4. Stakeholder Communication

Project managers can maintain transparency and build trust with stakeholders by regularly providing updates on project progress using EVM metrics. Additionally, being open about potential issues and challenges identified through EVM analysis demonstrates a commitment to accountability and proactive problem-solving.

5. Training and Education

Training project team members to ensure they understand EVM's concepts, calculations, and benefits. This training can be conducted through workshops, online courses, or on-the-job training. By investing in training, organizations can empower their teams to use EVM effectively and maximize its benefits.

6. Continuous Improvement

By regularly evaluating the effectiveness of EVM implementation and analyzing past projects, organizations can identify areas for improvement and make necessary adjustments. This ongoing process ensures that EVM remains a valuable tool for project management and contributes to overall organizational success.

Using EVM Software in Project Management

Earned Value Management system is a software tool designed to help project managers effectively track and analyze project performance using EVM principles. These systems automate many of the manual calculations involved in EVM, making it easier for project teams to gather data, analyze results, and make informed decisions. These tools often incorporate features such as:

  • Data entry: Simplified project data input, including planned value, earned value, and actual cost.

  • Automatic calculations: Automatic calculation of EVM metrics, reducing the risk of human error.

  • Visualizations: Graphs and charts to visualize project performance and identify trends.

  • Reporting: Customizable reports to provide stakeholders with clear and concise information.

  • Integration: Integration with other project management tools, such as scheduling software and collaboration platforms.

Popular EVM software options include:

  • Microsoft Project: A widely used project management tool with built-in EVM capabilities.

  • Primavera P6: A powerful project management solution with advanced EVM features.

  • Oracle Primavera Unifier: A comprehensive enterprise project management suite that incorporates EVM.

  • Deltek Acumen: A specialized EVM tool designed for large-scale projects.

Subscription banner

Subscribe to our updates!

Your information will be processed according to
EPAM SolutionsHub Privacy Policy.

Earned Value Management Certifications

There are several certifications available that validate your expertise in EVM:

1. Certified Earned Value Professional (CEVP): This certification, offered by the Project Management Institute (PMI), focuses explicitly on EVM. It demonstrates your knowledge and skills in applying EVM principles to project management.

2. Certified Cost Professional (CCP): While not exclusively focused on EVM, the CCP certification covers many cost management techniques, including EVM. It is a valuable credential for project managers who want to deepen their understanding of cost control and analysis.

3. Certified Project Controls Professional (CPCP): This PMI certification focuses on project controls, including Earned Value Management. It validates your expertise in project control techniques, including cost, schedule, and risk management.

Conclusion

Earned Value Management is a powerful tool for project managers. By integrating project scope, schedule, and cost data, EVM provides valuable insights into project performance. Following the steps outlined in this guide, project managers can effectively implement EVM to track progress, forecast future performance, and make data-driven decisions that enhance project success.

FAQ

What skills are necessary for implementing EVM in a project successfully?

Essential skills necessary for successful EVM implementation:

  • Technical skills: Proficiency in project management methodologies (e.g., Agile, Waterfall), understanding of EVM concepts and calculations, and using project management software with EVM capabilities.
  • Soft skills: Strong communication skills to effectively convey EVM data and insights to stakeholders, leadership skills to motivate team members and address challenges, and problem-solving skills to identify and resolve issues related to EVM implementation.
  • Continuous improvement: A commitment to learning and adapting EVM practices to meet evolving project needs.

What does EVMS stand for?

EVMS stands for Earned Value Management Systems. It's a framework or methodology for implementing EVM in projects, providing a structured approach for tracking and analyzing project performance.

Loading...

Related Content

View All Articles
Subscription banner

Get updates in your inbox

Subscribe to our emails to receive newsletters, product updates, and offers.

By clicking Subscribe you consent to EPAM Systems, Inc. processing your personal information as set out in the EPAM SolutionsHub Privacy Policy

Loading...